Backward scheduling is the scheduling technique that should be employed when due dates are important for a job order.

What is backward & forward scheduling?

Working forward from the commencement date is how forward scheduling is done. When planning backward, you start with the target completion date. Even if capacity is available, you might not be able to begin a job right away using backward scheduling. All tasks are scheduled backward from the end date.

Who uses backward scheduling?
Forward scheduling is typically used by make-to-stock manufacturers while backward scheduling is an option for make-to-order manufacturers (as well as those that make to stock by a sales projection). These two scheduling strategies can, however, also be combined. For various circumstances, businesses can employ a variety of approaches.