You have just been put in charge of a project that is already executing. While reviewing the project documentation, you discover that there is no WBS and you are approached by team members to add new components. You discover that there should be a WBS for the project. What is the BEST thing to do

Respuesta :

Answer:

Stop project work and create the WBS, and don’t let work continue until it’s created

Explanation:

The WBS refers to the Work breakdown structure in which the work is divided into many parts so that it is easy for each one to work upon it as it does not the pressure for only one person. It's better to divide the work so that it would be completed within a prescribed time

Since in the given situation, as there is no WBS so for that first we have to stop the work after that the WBS should be created and only after the work is started that means until WBS no work will started

Hence, the b option is correct