Given:
Service level = 95%
z = 1.65
Standard deviation = 8
Lead time demanded = 70
To find:
a. Safety stock level for BX-5
b. Appropriate reorder point
Solution:
The formula to calculate the safety stock is as follows,
[tex]\text{Safety stock }= \text{z}\times \text{Standard deviation}[/tex]
On plugging-in the values we get,
[tex]\Rightarrow \text{Safety stock} = 1.28\times8=10.24[/tex]
a. Therefore, the safety stock for BX-5 is 10.24
The formula to calculate the reorder point is as follows,
[tex]\text{Reorder point = Lead time demand + Safety stock}[/tex]
On substituting the values we get,
[tex]\Rightarrow \text{Reorder point} = 70+10.24 = 80.24[/tex]
b. The appropriate reorder point is 80.24