your factory has completed 150 of the 900 holiday orders. If you produce 150 units per day, how many more days are required to complete the order?

A. 4
B. 5
C. 6
D. 10

Respuesta :

5 more days are required to complete the order because 150 are already completed so 900-150 is 750 and divide it by 150 because that’s how many can be made in a day and get 5 it’ll take 5 more days to get to 900