​a _____ is a proactive effort to anticipate a risk and describe an action plan to deal with it.
a. ​risk response plan
b. ​risk management plan
c. ​risk balance plan
d. ​risk identification plan

Respuesta :

Answer:

b. ​risk management plan

Explanation:

this is true by definition, risk management involved forecasting risks, and laying out ways on how to manage them

  1. risk response plan is on how to reduce existing risks
  2. risk identification is to identify the risks of any open project
  3. risk balance plan is an analysis on how to maintain a balance on keeping safe and taking risks for greater benefit