Suppose that a person with a push mower can mow a large lawn in 5 ​hours, whereas the lawn can be mowed with a riding lawn mower in 3 hours. working​ together, how long will it take to mow the​ lawn?

Respuesta :

------------------------------------------------------------------
Push Mower
------------------------------------------------------------------
It takes 5 hours to complete the job
1 hour = 1/5 of the job

------------------------------------------------------------------
Riding Lawn Mower
------------------------------------------------------------------
It takes 3 hours to complete the job
1 hour = 1/3 of the job

------------------------------------------------------------------
Push Mower + Riding Lawn Mower
------------------------------------------------------------------
1 hour = 1/5 + 1/3 
1 hour = 3/15 + 5/15 
1 hour = 8/15 of the job.

------------------------------------------------------------------
Calculate time needed to complete
------------------------------------------------------------------
8/15 of the job takes 1 hour
8/15 of the job = 1 hour 

------------------------------------------------------------------
Divide by 8/15 on both side
------------------------------------------------------------------
8/15 ÷ 8/15 of the job = 1 ÷ 8/15 hour
Whole of the job = 1 x 15/8 hours
Whole of the job = 15/8 hours
Whole of the job = 1 7/8 hours

------------------------------------------------------------------
Answer: 1 7/8 hours
------------------------------------------------------------------