A factory needs to produce 1,800 jars of peanut butter on a certain day.They start production at 8:30 A.M. By 10:30 A.M., they have produced 600 jars of peanut butter.At what time will they complete the total number of jars that they need to produce

Respuesta :

It will take 6 hours.



I hope this helps you, and please don't forget to say thanks and give brainliest! It really helps out!
Let's figure the unit rate:

600 jars
----------- = 300 jars/hr
  2 hrs

They have already produced 600 jars, but need to produce 1800 total, or 1200 more than they have now.  At 300 jars/hr, that production will take 4 hours, and the job will be complete at four hours after 10:30 a.m., or, in other words, at 2:30 p.m.