Under management by exception, which differences between planned and actual results should be investigated? material and noncontrollable controllable and noncontrollable material and controllable all differences should be investigated

Respuesta :

Please correctly type the given choices next time since they are jumbled. I believe the correct choices are:

a. material and noncontrollable

b. controllable and noncontrollable

c. material and controllable

d. all differences should be investigated

 

The correct answer from the choices above is C.

Answer:

material and controllable