Sigma Corporation applies overhead cost to jobs on the basis of direct labor cost. Job V, which was started and completed during the current period, shows charges of $6,300 for direct materials, $9,600 for direct labor, and $5,472 for overhead on its job cost sheet. Job W, which is still in process at year-end, shows charges of $3,800 for direct materials and $5,800 for direct labor.
Required: 1a. Should any overhead cost be applied to Job W at year-end?
1b. How much overhead cost should be applied to Job W?
2. How will the costs included in Job W's job cost sheet be reported within Sigma Corporation's financial statements at the end of the year?
Complete this question by entering your answers in the tabs below.
Required 1a Required 1b Required 2 Should any overhead cost be applied to Job W at year-end?
Should any overhead cost be applied to Job W at year-end?
Required 1a Required 1b Required 2
How much overhead cost should be applied to Job W? Overhead cost Required 1a Required 1b Required 2
How will the costs included in Job W's job cost sheet be reported within Sigma Corporation's financial statements at the end of the year? Cost included in Job W's job cost sheet