Project A and B are mutually exclusive. Project A has a 5 year life and project B has a 7 year life. The cost of capital for both projects is 10%. The NPV of project A is $13.72 million while the NPV of Project B is $20 million. What is the Equivalent Annual Annuity for Project B?