The project aims to investigate the feasibility of constructing a hydroelectric dam from a technical, economic, and social point of view. The project charter created by the project manager on behalf of the project sponsor is now approved.
Which of the following processes should be performed next?
Develop Project Management Plan Identify Risks Identify Stakeholders Develop Project Charter

Respuesta :

(a) Develop Project Management Plan. The project's goal is to look into the technical and socioeconomic viability of building a hydroelectric dam. Following that, a project management plan should be developed.

A hydroelectric dam is one of the major components of a hydroelectric facility.. A dam is a significant man-made structure constructed to confine a body of water. Dams are built for a variety of purposes, including flood control and river flow management, in addition to hydroelectric power generation. Small-scale dams called weirs are constructed in certain rivers to regulate and gauge water flow. A sort of retaining structure known as a dam is a construction intended to produce sizable amounts of water that are known as reservoirs. These reservoirs can be used for water storage, water delivery, or irrigation. These constructions, which are erected on top of riverbeds, retain water and raise the water's level.

learn more about  hydroelectric dam here:

https://brainly.com/question/22969870

#SPJ4

ACCESS MORE