Based on this information available, 25 units are available to promise in week 5 and 5 units in week 7. So, the correct option is a week 5 and 7.
What is master production schedule?
The goods a company will create, when they will be produced, and in what quantities are specified in a master production schedule (MPS). An MPS connects production capacity and demand in the market. The goal of master production scheduling is to develop a practical strategy that reduces overstock and increases on-time delivery.
What are a master production schedule's primary purpose?
The MPS provides for the effective and optimal allocation of resources and takes demand variability into account, all of which help prevent material and item shortages. The increase in manufacturing organisation efficiency is likely the biggest benefit of MPS.
To know more about master production schedule, click here- brainly.com/question/18883082