The term ______ denotes specific efforts at identifying lessons learned on specific projects, whereas the term ______ was coined in the late 1980s from a research study paid for by the US Government.
A) project evaluation, retrospectives.
B) retrospectives, maturity model.
C) project evaluation, maturity model.
D) maturity model, retrospectives.
E) retrospectives, project evaluation.
B) retrospectives, maturity model.

Respuesta :

The term maturity model was first used in the late 1980s as a result of a research study funded by the US Government, whereas the term retrospectives denotes specific efforts at identifying lessons learned on specific projects.

What lessons have been learnt that will help initiatives both now and in the future perform better?

Lessons learned retrospectives aim to boost output on ongoing and upcoming initiatives.

What else do you call the process of examining a project's flaws?

Project managers can use the SWOT analysis, a strategic planning approach, to examine the advantages and disadvantages of their projects as well as any potential threats and opportunities.

What stage of the maturity model for project management does institutionalization of project management occur at?

Institutionalized procedures and organizational norms are covered in Level 3. In this stage of the paradigm, the management has formally documented the processes and standards and institutionalized them.

To Know more about retrospectives

https://brainly.com/question/14929870

#SPJ4