The activity rate for the setup activity cost pool is $200.
A cost pool means a grouping of individual prices, typically by department or service center. Price distribution are then made from the cost pool. For example, the cost of the maintenance department is calculated in a value pool and then distrubution to those departments using its services. In activity-based costing (ABC), Activity cost pool can be used to a general method to calculate production value.
Though, a manufacture can not be allocated for indirect values such as marketing and employee salaries.
Hence, the activity rate for the setup activity cost pool = 10,000 / 500
= $200