In written specifications, under the heading Painting and Finishing, which of the following would not be appropriate?
A. Surfaces to be included (interior and exterior).
B. Specific cations of materials to be used.
C. Application method and number of coats.
D. Number of painters to be used on the job.
E. Guarantee of quality and performance.
F. Completion date.

Respuesta :

Answer:

F. Completion date.

Explanation:

The completion date cannot be determined exactly before the job; it is also irrelevant to Painting and Finishing.

RELAXING NOICE
Relax