Audrey contracts CLEANOUT Inc. to upgrade the plumbing at each of her company's six offices. Audrey wanted the work to be done in two days, but CLEANOUT took three days to complete the work. Which of the following statements is most likely to be true in this scenario? Group of answer choices Both Audrey and CLEANOUT must consult a neutral third party to resolve their contractual dispute. CLEANOUT is entitled to a partial recovery under the contract. Audrey can sue CLEANOUT for material breach of contract. Audrey can refuse payment to CLEANOUT. CLEANOUT is entitled to full recovery under the contract.

Respuesta :

The statement that is said to be most likely to be true in this scenario are:

  • Both Audrey and CLEANOUT must consult a neutral third party to resolve their contractual dispute.
  • Audrey can sue CLEANOUT for material breach of contract.

What is the contract about?

In contract law, a "material" breach of contract is known to be a form of breach that took place when one part fails to carry out the contract and this strikes so well at the heart of the contract that it tends to renders the agreement "practically broken"

Note that The statement that is said to be most likely to be true in this scenario are:

  • Both Audrey and CLEANOUT must consult a neutral third party to resolve their contractual dispute.
  • Audrey can sue CLEANOUT for material breach of contract because it passed the due date.

Learn more about contract law from

https://brainly.com/question/25789642

#SPJ1