The project is going well. There is a scope change, and, as a result, a new team is brought in to assist the existing team in the new scope of the project. Upon arriving, the team asks to see where the the project currently stands. What do you show them

Respuesta :

Lanuel

As a project manager, you should show the new team a Gantt chart, so as to convey information about where the project currently stands.

What is a Gantt chart?

A Gantt chart can be defined as a type of bar chart that is typically used to graphically illustrate the amount of work done in certain periods of time and a project schedule, especially with information about the start and finish dates of a particular project.

Historically, Gantt chart was designed and developed by Henry L. Gantt in 1917. In this scenario, a Gantt chart should be shown to the new team, in order to convey information about the scope change and where the project currently stands to them.

Read more on Gantt chart here: https://brainly.com/question/26832885