The true statements about materials and requirements planning (MRP) outputs and their use are:
A. The secondary reports of MRP outputs are schedules of the planned order releases.
C. An exception report is generated if a major difference between actual performance and the MRP plan occurs.
D. MRP outputs include primary and secondary reports.
E. MRP assumes that parts produced or received from suppliers are defect-free and delivered as scheduled.
Materials and requirements planning (MRP) ensures that the right quantities of materials are available when needed for production. MRP produces three main reports, including:
Thus, the true statements about materials and requirements planning (MRP) outputs and their use are Options A, C, D, and E.
Learn more about materials and requirements planning (MRP) at https://brainly.com/question/6857359