A project manager is overseeing a complex custom CSM solution that has rigorous quality standards and tight schedule constraints. Since the project manager is working in a weak matrix environment, none of the resources are reporting to her functionally. She also does not have either the power or the budget to reward the team members to encourage and motivate them for their performance and contribution to the project. What kind of power should the project manager try to use in this type of situation

Respuesta :

Lanuel

The kind of power that the project manager should try to use in this type of situation is an: expert power.

A project manager refers to an individual who is saddled with the responsibility of planning, controlling, maintaining, and managing a group of people (team members) that are working under him or her, especially for the execution of a project.

In Project management, a project manager has different kinds of power and these include:

  • Referent power
  • Reward power
  • Coercive (penalty) power
  • Formal (legitimate) Power
  • Expert power

Expert power is one of the most effective kinds of power and it is typically possessed by a project manager that is a professional (expert) in a particular subject, field or project.

Since the project manager is working in a weak-matrix organizational environment and has no power or budget to reward her team members,  she should use her expert power to oversee the complex custom CSM solution project.

In conclusion, the kind of power that the project manager should try to use in this type of situation is an expert power.