In the context of sequencing, it should be noted that the difference between the completion time and the due date of a job is known as lateness.

Makespan simply means the time that's needed to process a given set of jobs. On the other hand, tardiness is the amount of time where the completion time exceeds the due date of the job.

The difference between the completion time and the due date of a job is simply referred to as lateness. In this case, the job is past its due date.