Respuesta :
Step-by-step explanation:
Explanation:
Less Men, means more Days {Indirect Proportion}
Let the number of days be x then,
27 : 36 :: 18 : x
[Please pay attention, we have written 27 : 36 rather than 36 : 27, in indirect proportion, if you get it then chain rule is clear to you :)]
=>27x = 36 * 18
=> x = 24
So 24 days will be required to get work done by 27 men..
Answer:
36 men can complete work in 18 days
so, one man can complete work in 18×36 days
Therefore, 27 can complete work in 18×36/27 = 24 days
Step-by-step explanation: