The Cost Sheet for Job 9 for the month of July is as follows:
Direct materials $2,250
Direct labor 1,350
Applied overhead 1,400
Total cost of manufacturing $5,000
Data for Job 9:
Estimated (applied) overhead = $1,400
Materials Requisitions:
Date Document Amount
July 1 M-46 $ 1,250
July 5 M-47 1,000
Total cost of materials = $2,250
Time Tickets:
Date Document Amount
July 1 T-33 600
July 5 T-34 450
July 10 T-35 300
Total cost of direct labor = $1,350
Thus, the total cost of producing Job 9 in July is $5,000.
Learn more about preparing a job cost sheet at https://brainly.com/question/16749090