Respuesta :
It is not true that b. You can't edit the values of inactive tasks when you inactivate tasks.
On Project Professional, you are allowed to inactivate a task. Should you do this:
- the task will still remain in the task list
- it will not however, affect the schedule
- there will be different formatting for inactive tasks
You will however be able to edit the inactive task as you see fit so it is not true that you can't edit values of inactive tasks.
In conclusion, inactivating a task does not mean that you will not be able to edit its values.