Answer: Dr Work in Process 6000
Dr Labor Rate Variance 552
Cr Labor Efficiency Variance 480
Cr Payroll 6072
Explanation:
First, we need to know the labor rate variance and the labor efficiency variance which will be:
Labor Rate Variance:
= 368 × (16.50-15)
= 552 U
Labor Efficiency Variance:
= 15 × (368-400)
= 480 F
Then, the journal entry to record labor variances will be:
Dr Work in Process 6000
Dr Labor Rate Variance 552
Cr Labor Efficiency Variance 480
Cr Payroll 6072