Answer:
a. $50,774.30
Explanation:
Present value of inflows = Cash inflow * Present value of discounting factor(rate%,t ime period)
Present value of inflows = $35,300/1.082 + $60,030/(1.082)^2 + $62,370/(1.082)^3 + $60,150/(1.082)^4 + $43,170/(1.082)^5
Present value of inflows = $32,624.77 + $51,275.96 + $49,237.27 + $43,886.06 + $29,110.24
Present value of inflows =$206,134.30
Project NPV = Present value of inflows - Present value of outflows
Project NPV = $206,134.30 - $155,360
Project NPV = $50,774.30