The purpose of rough cut capacity planning is to: Select one: a. place a time fence around the MPS. b. determine a production schedule that offers a rough order of magnitude. c. cut excess capacity from the MPS. d. assess the feasibility of the MPS. e. govern the length of the execution cycle.

Respuesta :

Answer:

The answer is "Option d".

Explanation:

To compute the estimated work on master capacity planning, the objective of basic resource allocation is utilized. It is then contrasted to a proven ability that enhances organizational MPS feasibility.

It verifies that you have enough ability at your disposal that satisfy the needs of your master's programs. It is a tool in long-term production scheduling for marketing and production to accomplish the ratio of the capacity required and accessible and to manage changes in the plan and/or looking.