Answer: [tex]10,000\ lb.ft[/tex]
Step-by-step explanation:
Given
Initial weight of the bucket is [tex]145\ lb[/tex]
It is lifted at constant rate and rate of sand escaping is [tex]0.5\ lb/ft[/tex]
At any height weight of the sand is [tex]w(h)=145-0.5h[/tex]
Work done is given by the product of applied force and displacement or the area under weight-displacement graph
from the figure area is given by
[tex]\Rightarrow W=\int_{0}^{80}\left ( 145-0.5h \right )dh\\\\\Rightarrow W=\left | 145h-\dfrac{0.5h^2}{2} \right |_0^{80}\\\\\Rightarrow W=\left [ 145\times 80-\dfrac{0.5(80))^2}{2} \right ]-0\\\\\Rightarrow W=11,600-1600\\\\\Rightarrow W=10,000\ lb.ft[/tex]