Answer:
Jaycee Corporation
The amount of job costs added to Work in Process in October is:
= $21,700.
Explanation:
a) Data and Calculations:
September 30, Work in Process:
Direct materials $2,300
Direct labor 3,800
Total WIP $6,100
Added in October:
Direct materials 2,800
Direct labor 6,300
Overhead 12,600 $21,700
Total job costs $27,800
The Work in process by October 1 is $6,100. Additional job costs added in October includes Direct materials, labor, and overhead, which totalled $21,700. Therefore, the total job costs for Job A3B is $27,800.