Answer:
Results are below.
Explanation:
Giving the following information:
Actual Hours Used 22,000
Actual Rate per Hour 15
Standard Rate per Hour 14
Standard Hours for Units Produced 23,500
To calculate the direct labor rate and efficiency variance, we need to use the following formulas:
Direct labor rate variance= (Standard Rate - Actual Rate)*Actual Quantity
Direct labor rate variance= (14 - 15)*22,000
Direct labor rate variance= $22,000 unfavorable
Direct labor time (efficiency) variance= (Standard Quantity - Actual Quantity)*standard rate
Direct labor time (efficiency) variance= (23,500 - 22,000)*14
Direct labor time (efficiency) variance= $21,000 favorable