The controller of Sandhill Industries has collected the following monthly expense data for use in analyzing the cost behavior of maintenance costs. Month Total Maintenance Costs Total Machine Hours January $2,880 3,820 February 3,273 4,364 March 3,928 6,546 April 4,632 8,619 May 3,491 5,455 June 4,844 8,730 (a1) Determine the variable-cost components using the high-low method. (Round answer to 2 decimal places e.g. 2.25.)

Respuesta :

Answer:

Variable cost per unit= $0.4

Explanation:

Giving the following information:

Month Total Maintenance Costs Total Machine Hours

January $2,880 3,820

February 3,273 4,364

March 3,928 6,546

April 4,632 8,619

May 3,491 5,455

June 4,844 8,730

To calculate the variable component using the high-low method, we need to use the following formula:

Variable cost per unit= (Highest activity cost - Lowest activity cost)/ (Highest activity units - Lowest activity units)

Variable cost per unit= (4,844 - 2,880) / (8,730 - 3,820)

Variable cost per unit= $0.4