7 men can complete a work in 52 days. In how many days will 13 men
finish the same work?

Respuesta :

matthewswatson
matthewswatson matthewswatson
  • 31-05-2021

Answer:

if 7 men complete the work in 52 days, it means a man will take (52×7=364)days to complete the same piece of work. therefore 13 men will take (364÷13)days which is equal to 28 days.

Answer Link

Otras preguntas

find "x"[tex] \frac{10}{5x - 9} = \frac{7}{9} [/tex]please explain your answer​
Why were scribes important In Sumerian government
NEED HELP PLEASE A vacant city lot is being turned into a neighborhood garden. The neighbors want to fence in a triangular section of the lot and plant flowers
I have 2457 dollar and u have the same I bought a ball a doll and cotton candy u tried to buy the same thing but u could not afford it .WHY???​
Please help!!!!!……………….PLEASEHELPPPP
They got her a special gold watch when she retired-because she ….at the company for 30 years. -has been working -had been working -had been worked
1. Describe the day on which the lottery takes place. How does the description of this day contrast with the events that take place later on? Cite textual evide
HEY PLEASE HELP AM DESPERATE!!!!!!
10-root18/root2 = a+broot2
You have been asked to cut a 1.5m roll of bubble wrap into 30 cm lengths, which are used to wrap CDs before posting to clients. How many pieces of bubble wrap w