Answer: See explanation
Explanation:
The material price variance will be calculated as:
= (Standard price - Actual price) × Actual quantity of material used
= ($2 - $4) × 500
= -$2 × 500
= $-1000
= $1000 Unfavourable
The material quantity variance will be:
= Standard quantity - Actual quantity) × Standard price
=[(450 × 2) -500] × $2.00
= (900 - 500) × $2.00
= 400 × $2.00
= $800 Favorable