The project management plan is the output of the planning process of project _____. a. scope management b. procurement management c. integration management d. quality management

Respuesta :

Hola lo siento no te entiendo

The planning for project management should be the result of the planning process of project integration management.

The information related to the project integration management is as follows:

  • It involved the coordination of all the parts of the projects.
  • It is the formal document that measured how the project should be executed, controlled & checked.

Therefore, the other options are incorrect.

Thus we can conclude that the planning for project management should be the result of the planning process of project integration management.

Learn more about the project here: brainly.com/question/15999858