Respuesta :

9514 1404 393

Answer:

  • 15 days
  • 7 workers

Step-by-step explanation:

The effort required to complete a task is often estimated in terms of person·days. Amy's barn-building task takes an effort of ...

  (5 workers)(9 days) = 45 worker·days

If there are only 3 workers, the time required is ...

  time = (45 worker·days)/(3 workers) = 15 days

__

If the barn is to be build in 7 days, the number of workers required is ...

  (45 worker·days)/(7 days) = 6 3/7 workers

A minimum of 7 workers are required to build the barn in 7 days or less. (6 workers will take 7 1/2 days, so aren't enough.)