samr2ahsa2rolcw samr2ahsa2rolcw 19-11-2016 Mathematics contestada 28 men can finish the job in 60 days. At the start of the 16 day, 5 men were laid off and after the 45th, 10 more men were hired. How many days were delayed in finishing the job? Please explain, step by step.