Answer:
the activity rate is $162
Explanation:
The computation of the activity rate is shown below:
= Estimated overhead cost ÷ Estimated activity
= $396,900 ÷ 2,450
= $162
Hence, the activity rate is $162
We simply applied the above formula so that the accurate activity rate could come