i) 18 men can complete a task in 12 days. How many more men should be employed to complete the same task in 9 days?

Relax

Respuesta :

xxhileilaaxx xxhileilaaxx
  • 28-02-2021

Answer:

the answer should be 12

Step-by-step explanation:

Answer Link

Otras preguntas

Write the name of the period that has the digits 486
why wheat flour is usually passed near a magnet before being packed?
Write the name of the period that has the digits 486
An average person in the United States throws away 4.5 × 10^–1 kg of trash per day. In 2013, there were about 3.2 × 10^6 people in the U.S. About how many kilog
The primary reason the United States advocated the Open Door policy in 1899 was to (A) consolidate good relations between the United States and European countri
How many pairs of whole numbers have a sum of 40?
The basic structural unit of the nervous system is the ? a) axon b) neuron c) red blood cell or d)white blood cell
How were colonial governments organized?
How many solutions does a system of linear equations in three variables have if in solving the system you correctly obtain the equation 12=12?
How do you write standard form 24 ten thousands