Respuesta :
It takes them 1 7/8 hrs to complete the job together.
How:
Fred = 3 hrs
Jason = 5 hrs
1/3x + 1/5x = 1/x
3x x 5x = 15 —> 3x/15 + 5x/15 = 15/15
3x + 5x = 8x —> 8x/15 = 1.875 = 1 7/8 hrs
How:
Fred = 3 hrs
Jason = 5 hrs
1/3x + 1/5x = 1/x
3x x 5x = 15 —> 3x/15 + 5x/15 = 15/15
3x + 5x = 8x —> 8x/15 = 1.875 = 1 7/8 hrs
Time would be taken by them if they worked together is 1 .875 hours .
What is work and time relationship?
Work is the effort applied to produce a deliverable or accomplish a task. A certain amount of time (T) is taken to complete a certain work (W).
Work Done = Time Taken × Rate of Work.
Rate of Work = 1 / Time Taken.
Time Taken = 1 / Rate of Work.
According to the question
Fred takes 3 hours to dig a garden.
Rate of Work of Fred to dig a garden = 1 / Time Taken.
= 1/ 3
Jason 5 hours to dig a garden.
Rate of Work of Jason to dig a garden = 1 / Time Taken.
= 1/5
Now, Time taken by them if they work together
Work Done = Time Taken × Rate of Work.
Let time taken be t
[tex]\frac{t}{3} + \frac{t}{5} = 1[/tex]
[tex]\frac{8t}{15} = 1[/tex]
t = [tex]\frac{15}{8}[/tex]
t = 1 .875 hours
Hence, Time would be taken by them if they worked together is 1 .875 hours .
To know more about work and time relationship here:
https://brainly.com/question/3854047
#SPJ2