What would a risk be based on the following information: Marty is 60 percent certain that he can get the facility needed for $45,000, which is $7000 less than what was planned for

Respuesta :

Answer:

Marty is 60 percent  sure  that he can save the project the amount of $7,000 which means that the  amount of $4,200 will tend to depict  the 60 percent certainty Amount  of the savings

Explanation:

What would the risk be based on the information given in a situation where he is 60 percent sure that he can get the facility needed for the amounts of $45,000 in which the amount is lower that the amount of $7000 that was planned for is that Marty is 60 percent  sure that he can save the project the amount of $7,000 which means that the amount of $4,200 which is simply calculated as (60%*$7,000) will tend to depict the 60 percent certainty Amount  of the savings.