Resource leveling is a network scheduling technique that seeks to assign nearly equivalent work units to each member of the project team. Group of answer choices True False

Respuesta :

Answer:

The given statement is false

Explanation:

Resource leveling is the process in the project management that see the allocation or distribution of the resources and solve the expected conflicts arise at the time when the over allocation is done and at the time when the project manager takes the responsibility of the project he required to plan regarding the allocation of resources accordingly

So as per the given scenario, the given statement is false