Answer:
1 → A ; 2 → C ; 3 → D ; 4 → B
Explanation:
From the given information, the table can be better structured as follows:
Job (Hours)
Resource A B C D
1 5 8 7 7
2 4 9 5 9
3 6 9 8 7
4 7 6 6 9
From the table, the allocation of resources is based on the minimum number of jobs i.e. time(hours) required to do all four tasks appropriately.
These are 1 → A ; 2 → C ; 3 → D ; 4 → B
Then, the time taken by this process is = (5 + 5 + 7 + 6)
= 23 hours