Answer:
Production rate = 1.66 pieces/min (Approx)
Explanation:
Given:
Average lead time = 18 minutes
Average work in process inventory = 30 pieces
Find:
Production rate
Computation:
Production rate = Average work in process inventory/Average lead time
Production rate = 30/18
Production rate = 1.66 pieces/min (Approx)