Answer:
The probability will be "0.205".
Step-by-step explanation:
The probability that perhaps the time remains greater than 9.5 days before the next shift will indeed be:
⇒ [tex]P(X>9.5)[/tex]
⇒ [tex]1-P(X<9.5)[/tex]
⇒ [tex]1-(1-exp(\frac{-9.5}{6} ))[/tex]
⇒ [tex]0.205[/tex]