Respuesta :
Answer:
The correct option is B
Explanation:
From the question we are told that
The mass of the pile is M
The height is H = 4 y
The vertical distance achieve during the first lift is [tex]h_1 = 3 y[/tex]
The time taken is [tex]t_1 = 4T [/tex]
The vertical distance achieve during the second lift is [tex]h_2 = y[/tex]
The time taken is [tex] t_2 = T [/tex]
Generally the velocity of the crane during the first lift is
[tex]v _1 = \frac{h_1}{t_1 }[/tex]
=> [tex]v _1 = \frac{3 y}{4T }[/tex]
Generally the velocity of the crane during the second lift is
[tex]v _2 = \frac{h_2}{t_2 }[/tex]
=> [tex]v _2 = \frac{ y}{T}[/tex]
Generally the power generated by the crane during the first lift is
[tex]P_1 = F_1 * v_1[/tex]
Here [tex]F_1[/tex] is the weight of the brick which is mathematically represented as
[tex]F_1 = M * g [/tex] , g is the acceleration due to gravity
So
[tex]P_1 = Mg * \frac{3y}{4T}[/tex]
Generally the power generated by the crane during the first lift is
[tex]P_1 = F_2 * v_2[/tex]
Here [tex]F_2[/tex] is the weight of the brick which is mathematically represented as
[tex]F_2 = M * g [/tex] , g is the acceleration due to gravity
So
[tex]P_1 = Mg * \frac{y}{T}[/tex]
The ratio of the first power generated to the second power is
[tex]\frac{P_1}{P_2} = \frac{Mg * \frac{3y}{4T} }{ Mg * \frac{y}{T} }[/tex]
=> [tex]\frac{P_1}{P_2} = \frac{3}{4}[/tex]
=> [tex]P_2 = \frac{4}{3} P_1[/tex]