If 10 men dig a ditch in 12 days .

Total man-days required to dig the ditch

= 10 men × 12 days

= 120 man-days

how long would 15 men take to dig it?

No of days required to finish the job by 15 men

= 120 men-days / 15 men

= 8 days

Answer: 8 days will be required to finish the job by 15 men