Answer:
Total cost= $43,344
Explanation:
Giving the following information:
Cardero Midwifery's cost formula for its wages and salaries is $2,280 per month plus $348 per birth.
The company planned for an activity of 118 births.
To calculate the budgeted total cost for wages and salary, we need to use the following formula:
Total cost= total fixed cost + unitary variable cost*number of births
Total cost= 2,280 + 348*118
Total cost= $43,344