Answer:
Total direct material variance= $1,000 favorable
Explanation:
Giving the following information:
Company had a favorable direct materials price variance of $3,000 and an unfavorable direct materials usage variance of $2,000.
To calculate the total direct material variance, we need to use the following formula:
Total direct material variance= price variance +/- quantity variance
Total direct material variance= 3,000 - 2,000
Total direct material variance= $1,000 favorable