Today (year 0), a new 7-megawatt (MW) solar panel farm is constructed at a direct cost of $10 million. The indirect cost of 10% of the direct cost was spent. Four years from today, a smaller 6-MW solar farm will be added to the existing farm. The cost indices of today and after 4 years are 400 and 600 respectively. If the cost-capacity factor is 0.75 for solar panel construction, what is the estimated total capital investment (direct indirect) for the smaller 6-MW farm