Answer:
1 and 2
Explanation:
A flexible budget is a budget in which there is a change in the volume or the change in activity so that it becomes so sophisticated
While on the other hand under the static budget the values would remain the same
So at the time of selection for activity levels, it should be within relevant change and expediency matter H
Hence, the first two statements are correct