a) While excavating, the Contractor hits a rock layer. Since the plans and soil report did not mention such rock, the contractor files a claim under: i. Force majeure. ii. Differing site conditions. iii. Design errors/omissions. iv. Unusual weather conditions. v. Changes in owner’s requirements.